Activity C is directly preceded by two activities,activity A and activity B.Activity A has an expected time of five and early start time of six.Activity B has an expected time of seven and an early start time of seven.Activity C has an expected time of ten.What is the early start for activity C?
Activity A,early finish is 6 + 5 = 11.
Activity B,early finish is 7 + 7 = 14.
The early start for Activity 7 is the larger of the two early finish times; so the time is 14.
Correct Answer:

Verified
Activity A,early finish is 6 +...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q27: Identify and describe the four parameters used
Q28: All the following activities are on the
Q29: The percentage of the project's scope that
Q30: Identify five of the critical factors in
Q31: Time,scope,and cost are positively correlated in project
Q33: Any activity that has not been completed
Q34: The path in a network diagram with
Q35: Draw a network diagram using the AON
Q36: In a PERT analysis,the "most likely time"
Q37: Identify and describe how leadership can impact