Using PERT,the Project Completion Time Closely Resembles What Distribution

Question 38

Multiple Choice

Using PERT,the project completion time closely resembles what distribution?


A) Uniform distribution
B) Poisson distribution
C) Normal distribution
D) Negative binomial distribution
E) Variance distribution

Correct Answer: