Multiple Choice
Regardless of the criteria differences among different types of projects,the most important criterion for project selection is
A) How the project will balance risk within the project portfolio
B) The project's fit to the organization strategy
C) Compliance
D) Nonfinancial
E) Profit
Correct Answer: