    An Activity That Has More Than One Predecessor Is a _________
Solved

An Activity That Has More Than One Predecessor Is a _________

Question 59

Question 59

Short Answer

An activity that has more than one predecessor is a _________ activity.

Correct Answer:

verifed

Verified

merge
Explanation: A merge act...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q54: In a project network, _ indicate activity

Q55: An element in the project that consumes

Q56: Tom is responsible for ordering hardware for

Q57: The assumption that all immediate preceding activities

Q58: Activities that can occur while an activity

Q60: When creating a project network, your primary

Q61: When completing the forward pass, the project

Q63: Activities that must occur immediately before a

Q64: A sequence of connected, dependent activities is

Q93: Experience suggests that when there are multiple

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2026) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines