Multiple Choice
Tom is managing a project team responsible for building a new office building that started this week.He notices that team members are trying out different behaviors to see what is acceptable to the project and personal relations.Which stage of development is the team in?
A) Norming
B) Storming
C) Performing
D) Adjourning
E) Forming
Correct Answer: