Multiple Choice
A positive situation where moving toward the optimum time can result in very real, large savings-this occurs when the network is:
A) Insensitive
B) Sensitive
C) Ahead of schedule
D) Shifting to the critical chain
E) Implementing a fast-tracking system
Correct Answer: