Multiple Choice
A tool used to monitor past project schedule performance, current performance, and to estimate future schedule trends is a simple line chart known as a:
A) Project schedule control chart
B) Gantt chart
C) PERT chart
D) Network diagram
E) Milestone chart
Correct Answer:

Verified
Correct Answer:
Verified