menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Operations Management Study Set 1
  4. Exam
    Exam 17: Project Management
  5. Question
    Activity 4-5 in a Network Diagram Has an Optimistic Time
Solved

Activity 4-5 in a Network Diagram Has an Optimistic Time

Question 32

Question 32

Multiple Choice

Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days.Its expected time is approximately:


A) 5
B) 6
C) 7
D) 8
E) 9

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q27: Consider the portion of a project depicted

Q28: What is the estimated standard deviation in

Q29: In the project network presented below, numbers

Q31: Which of the following is not characteristic

Q35: A method used for establishing a logical

Q36: Shortening activity durations is called:<br>A)Expediting<br>B)Crashing<br>C)Vendor management<br>D)Null nodes<br>E)Trade-off

Q37: What is the estimated slack time for

Q79: The costs associated with risk events tend

Q84: Which of the following is not true

Q90: The higher the node number, the longer

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2026) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines