Multiple Choice
Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 3 days (i.e., job A will take 3 more days to complete) , B will take 9 days, C will take 6 days, D will take 5 days and E will take 8 days.In what order will these jobs be scheduled if using the SOT priority rule for job sequencing?
A) A-B-D-E-C
B) A-D-C-E-B
C) D-C-A-B-E
D) B-E-C-D-A
E) E-D-A-B-C