Question 8

Multiple Choice

Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a production schedule.The remaining operating time necessary for completion of job A is 3 days (i.e., job A will take 3 more days to complete) , B will take 9 days, C will take 6 days, D will take 5 days and E will take 8 days.Which job should be scheduled last if using the SOT priority rule for job sequencing?


A) A
B) B
C) C
D) D
E) E