Sunk costs include any cost that
A) will change if a project is undertaken.
B) will be incurred if a project is accepted.
C) has previously been incurred and cannot be changed.
D) will occur if a project is accepted and once incurred,cannot be recouped.
E) is paid to a third party and cannot be refunded for any reason whatsoever.
Correct Answer: