Use the Earned Value Table (All Amounts Indicated Are Dollars)to

Question 48

Multiple Choice

Use the earned value table (all amounts indicated are dollars) to determine the earned value to the nearest hundred dollars given the indicated state of the project.  Activity 5101520253035 Plan % Complete  A 8503501,200100% B 400125525100%C1,2756501,925100%D28004,5003507,65095%E6804001,08075%F1258751,00080%G 30012001,50045% Monthly Plan 8507501,4003,4505,1801,1752,07514,880 Monthly Act 9006501,3503,8754,7808502,000\begin{array}{|l|l|l|l|l|l|l|l|l|l|}\hline \text { Activity } & 5 & 10 & 15 & 20 & 25 & 30 & 35 & \text { Plan } & \% \text { Complete } \\\hline \text { A } & 850 & 350 & & & & & & 1,200 & 100 \% \\\hline \text { B } & & 400 & 125 & & & & & 525 & 100 \% \\\hline \text {C} & & & 1,275 & 650 & & & & 1,925 & 100 \% \\\hline \text {D} & & & & 2800 & 4,500 & 350 & & 7,650 & 95 \% \\\hline \text {E} & & & & & 680 & 400 & & 1,080 & 75 \% \\\hline \text {F} & & & & & & 125 & 875 & 1,000 & 80 \% \\\hline \text {G } & & & & & & 300 & 1200 & 1,500 & 45 \% \\\hline \text { Monthly Plan } & 850 & 750 & 1,400 & 3,450 & 5,180 & 1,175 & 2,075 & 14,880 & \\ \hline \text { Monthly Act } & 900 & 650 & 1,350 & 3,875&4,780 & 850 & 2,000 & & \\\hline\end{array}


A) $16,900
B) $14,900
C) $14,400
D) $13,200

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions