Use the Information in the Table to Determine the Slack

Question 31

Multiple Choice

Use the information in the table to determine the slack time for Activity B.  Early  Early  Late  Late  Task  Predecesser  Duration  Start  Firish  Start  Firish A−8BA14CA238DC,B62326EC32FD,E3238\begin{array} { | l | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\ \text { Task } & \text { Predecesser } & \text { Duration } & \text { Start } & \text { Firish } & \text { Start } & \text { Firish } \\\hline \mathrm { A } & - & 8 & & & & \\\hline \mathrm { B } & \mathrm {A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & \mathbf { 2 3 } & \mathbf {8 } & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & \mathbf { 2 3 } & & \mathbf { 2 6 } & \\\hline \mathrm { E } & \mathrm { C } & & & \mathbf { 3 2 } & & \\\hline \mathrm { F } & \mathrm { D } , \mathrm { E } & & \mathbf { 3 2 } & & & \mathbf { 3 8 } \\\hline\end{array}


A) 6 days
B) 4 days
C) 2 days
D) 0 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions