Morton Reeves,a building subcontractor,submitted a bid for construction of a portion of a high-rise office building.The bid contained material errors in computation.Lago Corp. ,the general contractor,accepted the bid with the knowledge of Reeves' errors.Reeves:
A) must perform the contract unless he can show that Lago acted fraudulently.
B) must perform the contract according to the stated terms since his errors were unilateral.
C) can avoid liability on the contract only if his errors were not due to his negligence.
D) can avoid liability on the contract since Lago knew of his errors.
Correct Answer:

Verified
Correct Answer:
Verified
Q14: Misrepresentations can either be innocent or fraudulent.
Q15: Suppose that Reed is buying a crane
Q16: Nick,a real estate agent,decided to purchase a
Q17: When one of the parties offers a
Q18: The threat to institute a criminal prosecution
Q20: Concealment involves the active hiding of a
Q21: Ratification ends the right to rescind a
Q22: David entered into a contract to sell
Q23: Jim,the CEO of Maple,Inc. ,signed a few
Q24: Which of the following is a ground