Question 19

Multiple Choice

All of the following strategies can help a project team to develop realistic time estimates for project activities EXCEPT:​ 


A)  Add a significant buffer of time to each activity 
B)  Keep in mind time constraints such as learning curves, interruptions and competing priorities 
C)  Estimate times of completion of work without initial reference to a calendar 
D)  Verify all time estimates with the people doing the work