menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Process Technology
  4. Exam
    Exam 8: Project Scheduling
  5. Question
    If the Optimistic Time Is 3,the Most Likely Time Is
Solved

If the Optimistic Time Is 3,the Most Likely Time Is

Question 21

Question 21

Multiple Choice

If the optimistic time is 3,the most likely time is 5,and the pessimistic time is 7,then the expected time is


A) 6)
B) 5)
C) 15.
D) 4)

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q16: When making a forward pass through a

Q17: PERT is inexpensive to maintain and primarily

Q18: If prototype testing can be started only

Q19: Project Evaluation and Review Technique is a

Q20: Which of the following was chosen by

Q22: The standard deviation of the critical path

Q23: In CCPM,a definite amount of time that

Q24: Dependencies involving relationships between the project and

Q25: The CCPM method modifies the project schedule

Q26: Benefits of networking project activities include<br>A)an estimate

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2026) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines