Multiple Choice
If the cost estimate for a project is a basis for contract awards and performance reporting, it should be a(n) _____ estimate and as accurate as possible.
A) budgetary
B) definitive
C) rough order of magnitude
D) analogous
Correct Answer:

Verified
Correct Answer:
Verified