  5. Question
    If the Cost Estimate for a Project Is a Basis
Solved

If the Cost Estimate for a Project Is a Basis

Question 40

Question 40

Multiple Choice

If the cost estimate for a project is a basis for contract awards and performance reporting, it should be a(n) _____ estimate and as accurate as possible.


A) budgetary
B) definitive  
C) rough order of magnitude
D) analogous

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q27:  Determining the budget involves allocating the project

Q34:  _ costing helps to see a big-picture

Q36: A cost estimation tool which involves estimating

Q39:  If cost variance is a positive number,

Q41: A rough order of magnitude estimate can

Q42: Which of the following is true of

Q44: A(n)_ is the original project plan plus

Q55:  The project management plan and project funding

Q84:  Accountants define _ as a resource sacrificed

Q89:  Intangible costs can be easily measured in

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2026) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines