Which is the most essential rule that applies to project management?
A) Accurate time and cost estimates for all project activities are essential.
B) Backup redundancy of activities should be increased.
C) Expertise is not required to outline project activities and to sequence them correctly.
D) Multiple project leaders are preferred.
Correct Answer: