Identify a True Statement of the Critical Path Method (CPM)

Question 83

Multiple Choice

Identify a true statement of the Critical Path Method (CPM) .


A) In such a network,the critical path takes the shortest time to be completed.
B) The technique works by determining the critical path for interrelated activities with zero slack time.
C) Activities that are on the critical path are flexible and can be delayed.
D) A delay in the activities of a project can be ignored without considering additional resources.

Correct Answer: