Multiple Choice
During the implementation phase of the systems development life cycle (SDLC) ,in _____,the old and new systems run simultaneously for a short time to ensure the new system works correctly.
A) parallel conversion
B) phased-in-phased-out conversion
C) plunge conversion
D) pilot conversion
Correct Answer:

Verified
Correct Answer:
Verified