Multiple Choice
A project has an expected net present value of $50,000 with a standard deviation of the net present value of $20,000. Assume that NPV is normally distributed. What is the probability that the project will have a negative NPV?
A) 99.38%
B) 0.62%
C) 34.5%
D) 49.38%
Correct Answer:

Verified
Correct Answer:
Verified