Multiple Choice
The basic capital budgeting decision models, that is, NPV and IRR, handle risk by
A) ignoring it
B) assuming all cash flows are known with certainty
C) assuming all projects are of average risk and evaluating them based on expected values
D) using risk-adjusted discount rates to evaluate projects