Multiple Choice
Consider the following work breakdown structure: 
What is the probability that the critical path for this project will be completed within 200 days?
A) 0.8413
B) 0.9544
C) 0.9772
D) 0.9974
E) 0.9987
Correct Answer:

Verified
Correct Answer:
Verified