Multiple Choice
There are four resources and four jobs to be done. Assume there must be one-to-one matching between jobs and resources. The time required for each resource to do each job is as follows:
For the optimal schedule, what is the total number of hours required to complete these jobs?
A) 23 hours
B) 22 hours
C) 21 hours
D) 20 hours
E) 19 hours