What Is the Optimum Job Sequence for the Jobs Listed

Question 96

Multiple Choice

What is the optimum job sequence for the jobs listed below using Johnson's rule?  Job  Processing time (hrs)   Center 1  Center 2 d 1323 e 2313 f 1618 g 2017\begin{array} { c c c } \text { Job } & \begin{array} { c } \text { Processing time (hrs) } \\\text { Center 1 }\end{array} & \text { Center } 2 \\\text { d } & 13 & 23 \\\text { e } & 23 & 13 \\\text { f } & 16 & 18 \\\text { g } & 20 & 17\end{array}


A) e-g-f-d
B) d-g-f-e
C) d-f-g-e
D) e-d-f-g
E) f-e-d-g

Correct Answer: