Multiple Choice
The scheduling sequencing rule which always results in the lowest average completion (flow) time is the:
A) first come, first served (FCFS) rule.
B) shortest processing time first (SPT) rulE.
C) earliest due date first (EDD) rule.
D) least slack per operation first (S/O) rule.
E) run until slack happens (RUSH) rule.
Correct Answer:

Verified