Fixing a problem will often cost money; to minimize these costs it is best to find and fix the problem:
A) just before shipping our product to the customer.
B) immediately after we complete the last operation.
C) during the design phasE.
D) just before we begin the first production operation.
E) Regardless of when you fix the problem, costs are about the same.
Correct Answer: