A Company Is Designing a Product Layout for a New

Question 113

Multiple Choice

A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are: A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:   If the company wants the output rate to be equal to demand, what is the theoretical minimum number of workstations needed? A)  3 B)  4 C)  5 D)  6 E)  7
If the company wants the output rate to be equal to demand, what is the theoretical minimum number of workstations needed?


A)  3
B)  4
C)  5
D)  6
E)  7