Solved

The Jobs Listed Below Needed to Be Completed A) 476 Days
B) 60

Question 37

Multiple Choice

The jobs listed below needed to be completed. Assume that it is now day 140. If the jobs are sequenced according to shortest processing time rule, what is the average completion time?
 Job  Processing  Time (days)   Job due date  (days)   A 20180 B 30200 C 10175 D 16230 E 18210\begin{array} { | c | c | c | } \hline \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (days) }\end{array} & \begin{array} { c } \text { Job due date } \\\text { (days) }\end{array} \\\hline \text { A } & 20 & 180 \\\hline \text { B } & 30 & 200 \\\hline \text { C } & 10 & 175 \\\hline \text { D } & 16 & 230 \\\hline \text { E } & 18 & 210 \\\hline\end{array}


A) 47.6 days
B) 60.2 days
C) 94.0 days
D) 2.5 days
E) 238.0 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions