A Project Whose Critical Path Has an Estimated Time of 820

Question 111

Multiple Choice

A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before day (rounded to nearest day) .


A) 631
B) 689
C) 807
D) 833
E) 1009