Multiple Choice
A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before day (rounded to nearest day) .
A) 98
B) 112
C) 120
D) 124
E) 220
Correct Answer:

Verified
Correct Answer:
Verified