The Critical Path for the Network Activities Shown Below Is

Question 120

Multiple Choice

The critical path for the network activities shown below is __________ with duration __________.  Activity  Duration  Immediate  Predecessors  A 2−− B 4−− C 6 A,B  D 1 A,B  E 2 B,C,D \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Duration } & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} \\\hline \text { A } & 2 & - - \\\hline \text { B } & 4 & - - \\\hline \text { C } & 6 & \text { A,B } \\\hline \text { D } & 1 & \text { A,B } \\\hline \text { E } & 2 & \text { B,C,D } \\\hline\end{array}


A) A-D-E; 5
B) B-E; 6
C) B-D-E; 7
D) A-C-E; 10
E) B-C-E; 12