If After the ERP Project Starts and It Turns Out

Question 32

Multiple Choice

If after the ERP project starts and it turns out that the hardware for supporting the volume of transactions was undersized then it may be necessary to ________ the contract.


A) dissolve
B) change
C) re-bid
D) finalize

Correct Answer: