Multiple Choice
During the system implementation phase of the SDLC, once a system has passed testing, the organization installs the new system. Which of the following terms is used to refer to this activity?
A) beta testing
B) system conversion
C) agile development
D) system control
Correct Answer:

Verified
Correct Answer:
Verified