A trucking company has three bays for loading and unloading delivery trucks, identified as Bay A, Bay B, and Bay C. The company also has five trucks that all need to be loaded for deliveries within one hour using only the three bays. Truck 1 will take 45 minutes to load. Truck 2 will take 25 minutes to load. Truck 3 will take 15 minutes to load. Truck 4 will take 35 minutes to load. Truck 5 will take 45 minutes to load. Which of the following answer choices will accomplish all of the loading within one hour?
A) Load Truck 1 in Bay A, Trucks 2 and 4 in Bay B, and Trucks 3 and 5 in Bay C.
B) Load Trucks 1 and 2 in Bay A, Truck 4 in Bay B, and Trucks 3 and 5 in Bay C.
C) Load Trucks 1 and 4 in Bay A, Truck 2 in Bay B, and Trucks 3 and 5 in Bay C.
D) Load Truck 1 in Bay A, Trucks 3 and 4 in Bay B, and Trucks 2 and 5 in Bay C.
Correct Answer:

Verified
Correct Answer:
Verified
Q69: Katrina is a lawyer with Gotcha &
Q70: Bigtime Business is a Minnesota corporation that
Q71: Max is a lawyer who is representing
Q72: Paula and Gabe attend the formal gala
Q73: Peter, the president of Citywide Printing, and
Q75: Hannah is a paralegal working in the
Q76: Mary works for an attorney who handles
Q77: An investment company entered a contract with
Q78: Paula is a trial paralegal working with
Q79: Under Rule 33 of the Federal Rules