Multiple Choice
Which of the following choices cannot be a method of mistake and error proofing (poka-yoke) ?
A) Analysis of a process flow.
B) Electrical sensors which signal completion of a production phase.
C) Mechanical lift activation when a bin is full.
D) Visual cues that tell an employee when to stop paint dispersal.
Correct Answer:

Verified