Multiple Choice
Which measure would a lean practitioner use to determine or recognize abnormality in a process?
A) An and on which provides work instructions.
B) A process capability measurement.
C) A bar chart.
D) An Excel pivot table.
Correct Answer:

Verified
Correct Answer: