Multiple Choice
The Engineering News-Record (ENR) provides what is considered to be reliable general construction cost index (CCI) and building cost index (BCI) historic values. Which of the following statements best describes the use of ENR indexes?
A) Use CCI when labor costs are a significant portion of total cost
B) Use BCI costs for developing estimates of structures
C) A. and B.
D) None of the above
Correct Answer:

Verified
Correct Answer:
Verified