menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Trade & Technology
  3. Study Set
    Construction Project Management
  4. Exam
    Exam 5: Construction Tendering and Contract Management
  5. Question
    The Critical Path Is
Solved

The Critical Path Is

Question 19

Question 19

Multiple Choice

The critical path is


A) The longest path of the network
B) The shortest path of the network
C) The average duration path of the network
D) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q14: Ladder leading to landing should be extended

Q15: Mobilization advance<br>A)Shall be 2 to 5 %

Q16: The time activity consumes in most adverse

Q17: The float of critical activity is always<br>A)Maximum<br>B)Minimum<br>C)Zero<br>D)None

Q18: A dummy activity in a network<br>A)Is represented

Q20: The notice inviting tender should published in

Q21: Form no .........is used for material at

Q22: PERT analysis is based upon<br>A)Optimistic time<br>B)Pessimistic time<br>C)Most

Q23: Which of the following is an activity<br>A)Excavation<br>B)Curing<br>C)Laying

Q24: Which are the criteria to be checked

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2026) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines