Multiple Choice
The design firm notices that a large item on a project has accidently been left off the specifications. The design firm needs to inform bidders of the changes in the contract documents and the contract has not yet been awarded, they should issue:
A) A change order
B) An addendum
C) An alternative specification form
D) A condition change form
Correct Answer:

Verified
Correct Answer:
Verified