Multiple Choice
If the Owner cannot extend the completion date after a delay
A) the Contractor will need to perform some sort of acceleration
B) the project will have to be canceled
C) the General will have to hold Subcontractors accountable for the delay
D) the Contractor has no recourse but to sue the Owner and the Design Professional
Correct Answer:

Verified
Correct Answer:
Verified
Q11: Once a contract is signed, usually the
Q12: ""Construed against the drafter"" is<br>A) no longer
Q13: The extra costs related to directed acceleration
Q14: Liquidated damages are<br>A) seldom enforced<br>B) always enforced<br>C)
Q15: Liquidated damages are usually covered by flood
Q16: Trade stacking usually occurs at the beginning
Q17: In regard to use of float<br>A) the
Q18: A concurrent delay is when two or
Q19: Float is often seen as belonging to<br>A)
Q21: ""Time is of the essence"" clauses are