Solved

A Project Has an Expected Net Present Value of $50,000

Question 34

Multiple Choice

A project has an expected net present value of $50,000 with a standard deviation of the net present value of $20,000. Assume that NPV is normally distributed. What is the probability that the project will have a negative NPV?


A) 99.38%
B) 0.62%
C) 34.5%
D) 49.38%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge