The Primary Difference Between a Work Breakdown Structure and a Work

Question 20

Multiple Choice

The primary difference between a work breakdown structure and a work sequence draft is that the work sequence draft shows ___________________.​


A) the additionally deployment tasks
B) ​the estimated effort of tasks
C) ​the day to day assignments
D) ​the sequence of tasks