Multiple Choice
Adrian is the project manager of the NHP Project. In her project there are several work packages that deal with electrical wiring. Rather than to manage the risk internally she has decided to hire a vendor to complete all work packages that deal with the electrical wiring. By removing the risk internally to a licensed electrician Adrian feels more comfortable with project team being safe. What type of risk response has Adrian used in this example?
A) Mitigation
B) Transference
C) Avoidance
D) Acceptance
Correct Answer:

Verified
Correct Answer:
Verified
Q77: During qualitative risk analysis you want to
Q78: Joan is the project manager of the
Q79: Which of the following approaches can be
Q80: Which of the following requires all general
Q81: Certification and Accreditation (C&A or CnA) is
Q83: You are the project manager of the
Q84: Which of the following system security policies
Q85: Which of the following RMF phases identifies
Q86: In what portion of a project are
Q87: Which of the following professionals plays the