Solved

Your Organization Has Named You the Project Manager of the JKN

Question 60

Multiple Choice

Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?


A) Project costs will increase.
B) The amount of hours a resource can be used will diminish.
C) The project will take longer to complete, but risks will diminish.
D) Project risks will increase.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions