You Are the Project Manager of the NNH Project

Question 53

Multiple Choice

You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's schedule performance index?


A) 1.06
B) 0.93
C) -$37,800
D) 0.92