Which of the following processes is described in the statement below? "It is the process of implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new risks, and evaluating risk process effectiveness throughout the project."
A) Perform Quantitative Risk Analysis
B) Perform Qualitative Risk Analysis
C) Monitor and Control Risks
D) Identify Risks