Multiple Choice
David is the project manager of HGF project for his company. David, the project team, and several key stakeholders have completed risk identification and are ready to move into qualitative risk analysis. Tracy, a project team member, does not understand why they need to complete qualitative risk analysis. Which one of the following is the best explanation for completing qualitative risk analysis?
A) It is a rapid and cost-effective means of establishing priorities for the plan risk responses and lays the foundation for quantitative analysis.
B) It is a cost-effective means of establishing probability and impact for the project risks.
C) Qualitative risk analysis helps segment the project risks, create a risk breakdown structure, and create fast and accurate risk responses.
D) All risks must pass through quantitative risk analysis before qualitative risk analysis.
Correct Answer:

Verified
Correct Answer:
Verified
Q269: You are the project manager for your
Q270: You work as a project manager for
Q271: In 2003, NIST developed a new Certification
Q272: Diana is the project manager of the
Q273: The Information System Security Officer (ISSO) and
Q275: Which of the following objectives are defined
Q276: Harry is the project manager of the
Q277: A part of a project deals with
Q278: What does RTM stand for?<br>A) Resource Testing
Q279: A Web-based credit card company had collected