Multiple Choice
Beth is the project manager of the BFG Project for her company. In this project Beth has decided to create a contingency response based on the performance of the project schedule. If the project schedule variance is greater than $10,000 the contingency plan will be implemented. What is the formula for the schedule variance?
A) SV=EV-PV
B) SV=EV/AC
C) SV=PV-EV
D) SV=EV/PV
Correct Answer:

Verified
Correct Answer:
Verified