Multiple Choice
Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?
A) Sammy is correct, because organizations can create risk scores for each objective of the project.
B) Harry is correct, because the risk probability and impact considers all objectives of the project.
C) Harry is correct, the risk probability and impact matrix is the only approach to risk assessment.
D) Sammy is correct, because she is the project manager.
Correct Answer:

Verified
Correct Answer:
Verified
Q280: A project team member has just identified
Q281: Which of the following NIST Special Publication
Q282: Neil works as a project manager for
Q283: Which of the following statements is true
Q284: Which of the following refers to an
Q286: Which of the following is not a
Q287: You are preparing to start the qualitative
Q288: Which of the following NIST Special Publication
Q289: Walter is the project manager of a
Q290: You and your project team are identifying